Configure your dates

Jira Product Discovery allows you to play with the timeline's time scale by enabling you to select the start date of your year.

Before you begin

  • In order to configure the timeline dates, you need site admin permissions.

  • If you change the start date of your year, the change gets applied to all existing projects across your site.

Steps

  1. To configure the year, go to the top of the screen and select

  2. Click Products, and under Jira Product Discovery, select Dates.

  3. Select the start month of the year and Save.

Once you have updated the dates, you can always change them again by accessing the configuration options through the timeline settings panel. Click the dates in the timeline header and click Edit next to The year starts in…

The change is also reflected in the date fields. To change a quarter, click the date field name and make the changes in the menu.