Change the date field used to schedule work items in your plan
このページでは、Jira Cloud Premium と Enterprise の一部としてのみ利用できる高度な計画機能について説明します。
By default, your plan uses the Due dates field when scheduling work items. You can choose to replace this with any date field that’s been added to your plan.
Looking at your timeline, the date fields that are used to schedule work items are marked with a D in the Date column. If your dates have an S next to them, then your plan is scheduling work based based on sprint dates. If your dates have an R next to them, then your plan is scheduling work based on release dates.
To change which date field your plan uses:
Next to your plan’s name in the sidebar, select More actions (•••), then Plan settings.
On the Estimation and scheduling page, use the drop down menus to select the fields you want to use to schedule the start and end dates of your work items.
この内容はお役に立ちましたか?