Change how your plan handles dependencies in the same iteration
このページでは、Jira Cloud Premium と Enterprise の一部としてのみ利用できる高度な計画機能について説明します。
Planners have the option to change whether dependent work items that have been scheduled to the same iteration show as off-track dependencies. This applies when scheduling work by sprints on the timeline and in the program board.
Most planners won’t need to touch this setting. However, we recommend turning this setting off if you’re using the auto-scheduler.
To change how concurrent dependencies are displayed in your plan:
Next to your plan’s name in the sidebar, select More actions (•••), then Plan settings.
On the Estimation and scheduling page, use the checkbox next to Dependent work items can be scheduled to the same iteration.
この内容はお役に立ちましたか?